Tuesday, October 15, 2013

The end of Central Avenue

I never did wrap this thing up.
Here are the last few pictures from the renovation.
All the work is complete, we have successfully completed the condo conversion and and getting ready for the next project.



















Monday, August 22, 2011

Sheetrock!

So to bring everyone up to speed here are a series of pictures.

First up, our sound isolation system.
Using rubber isolators, metal hat channel, two layer of sheet rock, and a product called green glue, we hope to acoustically separate the two units.

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

The reason for the strips of Sheetrock on the track is because I messed up the depth of our light boxes... they were sitting between 1/8" and 1/2" two low... so I had to shim the entire ceiling to make sure the lights came our correctly.

Photobucket

Photobucket

Photobucket

Here a few more pictures of the rest of the house.

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Sheet Rocked stacked and ready to go.
Photobucket

Photobucket

Once our isolation system was in place, it was time to Sheetrock.
We hired a team of guys to come in and knock this out. If I had to guess, it would have taken Evan, Alec and myself at least 6 weeks to hang the rock, tape and mud it.
After two days, the Sheetrockers completed about 90% of the house. We will have a screw inspection tomorrow and they will most likely be done tomorrow or Wednesday.

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Photobucket



Monday, August 15, 2011

Update Time

So yeah..... I have really neglected my house blogging for the last 5 months or so... but if anyone actually comes back to look at this, here's an update.

All electrical work is completed, inspected and signed off
All plumbing work is completed, inspected and signed off
All mechanical work is completed, inspected and signed off
All insulation work is completed, inspected and signed off

In fact, we now have the entire house signed off to the point we can start to sheet rock.
We have also decided that we are going to pay someone to sheet rock it because it should knock a month off the project...

Here are a few pictures of the insulation and our attempts to stiffen up the floor above.
Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Wednesday, February 2, 2011

Currently

I know, I know… It’s been a month since my last post.
Well the lack of posting means progress with working.
It has been nonstop insanity since Bay Concrete wrapped up.
As of right now the electrical is about 95% roughed in, the plumbing should be all but wrapped up by the end of this weekend, and we still have all the ductwork to do.

So… here are some pictures to catch you up from the last time I posted.

Photobucket

Photobucket

Photobucket

We pulled up the old flooring in the bathroom because it was in such bad shape
Photobucket

Photobucket

Photobucket

Photobucket

We dropped the ceiling for the new living room about ½” to make it perfectly level
Photobucket

Built the rest of the wall that will hold the TV
Photobucket

Photobucket

Photobucket

Kitchen lighting
Photobucket

Photobucket

Photobucket

Photobucket

Photobucket

Electrical Panel
Photobucket

Photobucket

New shutoff valves for plumbing
Photobucket

Garage Door was installed
Photobucket

Photobucket

Ramps were built
Photobucket

General Mess
Photobucket