The next steps....
1. Wait for the Bureau of Street-Use and Mapping to process our endorsement letters.
2. Bureau of Street-Use and Mapping will send required paperwork to the Department of Public Works @ City Hall
3. Department of Public Works will then put paperwork inline to get a hearing date.
4. Hearing Date gets assigned.
5. Notification is sent out 10 days prior to hearing to all neighbors within 120 feet of our lot.
6. Our case is brought before the Supervisors of the Department of Public Works.
7. Supervisors review case and listen to any public comments.
8. Hell freezes over
9. We get our Permits.
As of right now, we are on step 1.
And as my bother put it so simply, "Insanity"
Monday, March 22, 2010
Monday, March 15, 2010
Freaking City
1/9/09 - Submit First Set of Plans to the city
1/13/09 - Plans Sent to the correct department
2/2/09 - Plans put on hold pending "Historical Review"
2/14/09 - Information submitted for "Historical Review"
10/7/09 - Plans for changing the facade approved
10/9/09 - Building Plans sent to "Building Plan Review Service"
10/14/09 - Building Plan Review Service start looking at plans
10/15/09 - Structural and Architectural Plans Approved
10-19-09 - Plans sent to "Street use and Mapping"
10-20-09 - Put on hold Pending sidewalk encroachment drawings
10-25-09 - Submitted encroachment drawings
2/1/10 - Encroachment drawing "approved as noted"
2/11/10 - Encroachment drawing resubmitted
2/15/10 - City Changes its mind on encroachment. - Plans put on hold Pending 51% sign off from all neighbors within 120 feet of each corner of our lot.
3/9/10 - We get our 12th sign off (54%) from neighbors and submit to City
3/15/10 - Waiting for City to set Court Date to allow for neighbors to Protest
1 Year, 2 Months, and 6 Days Later - Still waiting for final approval.
What else can they throw at us?
Subscribe to:
Posts (Atom)